Build dashboard

Progress by hall, open snags, purchasing risk and safety — the same live picture Si answers from.

Sample data
Crew board
Lumcloon DC · Day 186 Sample data
On site now
47
Open snags
18
Unbilled variations
€214k
LTI this month
0

Progress by hall / phase

Hall 1 · fit-out72%
Hall 2 · envelope54%
Hall 2 · fit-out28%
Plant · energisation31%
External works61%

Active blockers

ItemOwnerStatus
Hall 2 fire-stopping cert Ashbourne Fire Blocking
Cable tray shortfall PO-1842 Northframe ETA +1 day
Hoist window clash Fri Si / Rivermark Rebooked

Snags

RefAreaAge
SN-441Hall 1 riser seal3dOpen
SN-438Plant bund coating5dOpen
SN-429Gate 3 lighting1dAssigned

Purchasing & variations

ItemValueStatus
VAR-92 additional containment€48kUnbilled
VAR-88 Hall 2 overtime€31kUnbilled
PO-1842 cable tray€19kIn transit
PO-1799 raised floor€62kReceived

Safety today

Briefings signed
47/47
Near misses
1
Permits live
6
Certs expiring <14d
3