Operations view
Build dashboard
Progress by hall, open snags, purchasing risk and safety — the same live picture Si answers from.
On site now
47
Open snags
18
Unbilled variations
€214k
LTI this month
0
Progress by hall / phase
Active blockers
| Item | Owner | Status |
|---|---|---|
| Hall 2 fire-stopping cert | Ashbourne Fire | Blocking |
| Cable tray shortfall PO-1842 | Northframe | ETA +1 day |
| Hoist window clash Fri | Si / Rivermark | Rebooked |
Snags
| Ref | Area | Age | |
|---|---|---|---|
| SN-441 | Hall 1 riser seal | 3d | Open |
| SN-438 | Plant bund coating | 5d | Open |
| SN-429 | Gate 3 lighting | 1d | Assigned |
Purchasing & variations
| Item | Value | Status |
|---|---|---|
| VAR-92 additional containment | €48k | Unbilled |
| VAR-88 Hall 2 overtime | €31k | Unbilled |
| PO-1842 cable tray | €19k | In transit |
| PO-1799 raised floor | €62k | Received |
Safety today
Briefings signed
47/47
Near misses
1
Permits live
6
Certs expiring <14d
3